Module: Master planning
First Available In 10.0.38
Find out more at https://go.microsoft.com/fwlink/?linkid=2244803Lifecycle State: Can Be Disabled:

Content Author Info

Created By Nathan Clouse
Created On 2023-12-31
Updated By Nathan Clouse
Update On 2024-01-12

This functionality is applicable when the Use the specified BOM or formula version or route version is set to Yes. A new parameter is introduced in the coverage group to indicate if existing supply (e.g. on-hand) should be prioritized over the required BOM/route. When setting this parameter to Yes if existing supply (e.g. on-hand) should be used for fulfilling the item demand if available. Set to No if the a planned production order for the specified BOM/route should be created to supply the item, even if there is available existing supply.